Government and CCAA process 80% of the renewable parks that were going to ‘expire’

Date: November 29, 2023 Time: 01:32:37

The Government and the autonomous communities are advancing at a forced march in the processing of the Environmental Impact Declarations (DIA) that expect miles of renewable megawatts. This Wednesday ends the term given by the Ministry for Ecological Transition for its resolution (whether positive or negative) and many developers are waiting to find out whether or not they lose the access and connection permits to the network that were awarded at auction in 2020.

In December, projects totaling around 80,000 megawatts (60,000 solar and 19,000 wind) will remain pending processing, and industry sources tell La Información that 80% of emerging reports are expected to be resolved. It remains to be seen how many of these projects have received approval and resulted in a negative DIA. In the last month, it has been possible to see how day after day the Official State Gazette (BOE) and the official gazettes of the autonomous communities publish a long list of resolutions. This Monday there were 15 in the BOE.

The Ministry for the Ecological Transition manages the process for projects of more than 50 MW, while the autonomous communities are in charge when the capacity is lower. The third vice president and head of the department, Teresa Ribera, has assured that 100% of the renewable projects that the Government will process will be resolved tomorrow, January 25.

legal battle

Companies must present a series of economic guarantees for the processing of the request for access to the transmission or distribution network and all those that do not receive the environmental report on time will lose them, in accordance with article 26 of Royal Decree 1183/2020. “The expiration of the access and connection permits in accordance with the provisions of article 26 of this royal decree, will mean the immediate execution by the competent body for the issuance of the administrative authorizations of the economic guarantees presented for the processing of the application. of access to the transmission or distribution network, as applicable in each case”, literally states the text.

However, as it is a bureaucratic problem due to the enormous traffic jam in public instances, companies can take legal action against the Administration for not complying with the deadline process. Despite the fact that the deadline for obtaining the DIA ends this Wednesday, Redeia has until February 25 to evaluate the permits that expire and issue a formal ruling.

The DIA, a procedure with which the Government tried to prevent speculation with the land near the connection points, has turned out to be an unprecedented bureaucratic jam in the Spanish Administration. Officials from the different regional governments have been working against the clock for almost two months to release the maximum number of projects. The Government concluded in December 2021 an extension of the term for an additional 9 months to obtain the DIA and Ribera has refused to allow another postponement.

The wind sector has requested a six-month extension for the Administration to finish analyzing all the projects. It also defends that the administrative regulations be reviewed so that “situations of massive accumulation of applications can be managed, giving visibility and certainty to promoters about the viability and probability of success of their projects.”

Valencia, “sure” that it will comply

By communities, Galicia reported last Thursday that it has completed 92 of the 140 projects that have been presented in the region, of which 66 have obtained a favorable environmental declaration and the other 26, negative. For his part, the president of the Valencian Community, Ximo Puig, has been “sure” that on January 25 he will resolve all the files in the hands of the autonomy, which involves three different ministries to authorize the projects.

For its part, in Catalonia there are 1,967 MW requested for photovoltaic installations, of which 89 have been authorized and 95 rejected -as of January 23-. Of the total, 173 MW must be processed by the Ministry. For wind farms, 830 MW have been requested in the Catalan region (485 MW in the hands of the central Executive), without having authorized any but 49 MW have been denied.

Fast Track

With the aim of ending the speculation that exists around renewable energy projects, the Executive will only process those that have won access to the electricity grid in competition. This is stated in the Royal Decree-Law in which the sixth anti-crisis package is developed as a consequence of Russia’s invasion of Ukraine. The text also includes a procedure for termination of environmental damage for renewable projects of an exceptional and transitory nature, which opens a faster path for processing.

In this way, projects that are not located in areas of the Natura 2000 Network, in protected natural areas defined in the Natural Heritage and Biodiversity Law and in the marine environment will be exempted from environmental assessment. Those for the construction of overhead electric power lines with a voltage equal to or greater than 220 kilovolts and a length greater than 15 kilometers will have to comply with the requirement.

* This website provides news content gathered from various internet sources. It is crucial to understand that we are not responsible for the accuracy, completeness, or reliability of the information presented Read More

Puck Henry
Puck Henry
Puck Henry is an editor for ePrimefeed covering all types of news.
RELATED ARTICLES

Most Popular

Recent Comments