At the power supply centre, Rosseti Tyumen specialists repaired the power transformer. As part of the work, new 110 kV high-voltage bushings, air-drying filters, gas and jet relays were installed. In addition, shut-off valves were inspected, power and control cables were replaced, and transformer oil was dried and cleaned. All planned events were carried out without restricting the supply of electricity. Their cost exceeded 8 million rubles.
It should be noted that the planned repair of the 110 kV Promzone substation was carried out within the framework of the energy company’s production program, the main goal of which is to prepare the Ugra power grid complex for the autumn-winter period of 2024-2025.
Press release provided by Rosseti Tyumen JSC.